thuyan7921 6/19/2023 3:43:12 PM
You create a list of tasks for a project and determine which tasks the team must complete before another task can begin. What type of tasks have you identified?1 / 1 pointCritical pathsMilestonesSubtasksDependencies
1 0
thaochau0123

Dependencies