As project manager, you approve a team member’s request to change the order of their tasks because they think it will be more efficient. However, this change disrupts another team member’s work process: they need to do two additional tasks not related to the project’s goal. What is happening on this project? 1 / 1 pointA. The project is iterating.B. The project is going out-of-scope.C. The project is becoming more efficient.D. The project is staying in-scope.