When creating a critical path, what does a network diagram help visualize? Select all that apply.0.75 / 1 pointWhich non-essential tasks are not on the critical pathWhich skilled teammate can work on each taskThe path of work from the start to the end of the projectThe tasks that can be performed in parallelYou didn’t select all the correct answers
1 0
huynhthiquyena32018

The path of work from the start to the end of the project

The tasks that can be performed in parallel

 