As a project manager, you’re identifying task dependencies. Task B cannot start until Task A has started. Which type of dependency does this situation represent?  Finish to Start (FS)Start to Finish (SF)Finish to Finish (FF)Start to Start (SS)
2 4
tenngoc1791999

Start to Start (SS)

khanhminh799

SS